General Overview of Proposed Work
in our 100-year-old North Building
2024-2027
(This is what we know right now. Schedules will definitely evolve.)
August - September 2024
Demolition of Area to be Renovated for Photo Archives Multi-climate Suite
(Rm 328, third floor)
August 2024-December 2024
Investigative Work in Walls and Ceilings
Finalizing of Construction Documents
Culling and Cleaning of Office and Storage Spaces
Planning and Preparation for Collections Movement(s)
September 2024 - March 2025
Construction of Photo Archives Multi-climate Suite
(Rm 328, third floor)
November 1, 2024
Begin Demolition and Abatement on First Floor
January 2025 – October 2025
Work in West Side of Basement
Work in NE Section of First Floor
January 2025 – April 2026
Replacement of Window Glass on all Three Floors
(done in three phases)
February 2025 – September 2025
Work in Central Basement Area
February 2025-June 2025
Work on First Floor
(excluding Perishables Vault, Pottery Vault, Conservation Lab)
March 2025 – April 2026
Work in East Side of Basement